Kingsley Passivhaus

download as PDF
Download
as PDF
Retrofit of a 1940s semi to full passivhaus standard
Images Graphs Figures Description Strategies Building

Kingsley Passivhaus : Project images

Click on image to preview full size

File_003.jpg
IMG_0049_2.jpg
IMG_0127.jpg
IMG_0479.jpg
kingsley1.jpg
kingsley10.jpg
kingsley16.jpg
CO2 emissionsPrimary energy requirement
Energy target
PassivHaus

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Renewable electricity generation This project has used the contributions from renewable electricity generation equipment to either meet the Retrofit for the Future target or otherwise reduce the Primary energy requirement and CO₂ emissions associated with the project.

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use 2000 kWh/yr 2000 kWh/yr 2195 kWh/yr
Natural gas use6400 kWh/yr 1960 kWh/yr 1926 kWh/yr
Oil use- - -
LPG use- - -
Wood use- - -
mains gas - - -
 Pre-developmentForecastMeasured
Primary energy requirement 126 kWh/m².yr 74 kWh/m².yr 79 kWh/m².yr
Annual CO₂ emissions 26 kg CO₂/m².yr 16 kg CO₂/m².yr 17 kg CO₂/m².yr
Annual space heat demand 80 kWh/m².yr 16 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
PV3000 kWh/yr 3000 kWh/yr
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
-3 kWh/m².yr 2 kWh/m².yr
Annual CO₂ emissions
offset by renewable generation
-2 kg CO₂/m².yr -1 kg CO₂/m².yr

Calculation and targets

Whole house energy calculation method PHPP
Other whole house calculation method-
Energy target PassivHaus
Other energy targets-
Forecast heating load 10 W/m² demand

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test01 March 20160.27m³/m².hr @ 50 Pascals

Project description

StageOccupied
Start date01 February 2015
Occupation date02 April 2016
Location Kingsley Cheshire  England
Build typeRefurbishment
Building sectorPrivate Residential
Property typeSemi-Detached
Construction typeMasonry Cavity
Other construction type200
Party wall construction230mm solid brick
Floor area 98
Floor area calculation method Treated Floor Area (PHPP)
Building certification  Passivhaus certified building Passivhaus certified building

Project Team

OrganisationChris Copeman
Project lead personChris Copeman
Landlord or ClientChris Copeman and family
ArchitectGil Shalom
Mechanical & electrical consultant
Energy consultantGreen Building Store
Structural engineer
Quantity surveyor
Consultant
ContractorChris Copeman

Design strategies

Planned occupancyThree people, all out to work or school on weekdays.
Space heating strategyHeating from mains gas fired boiler feeding radiators
Water heating strategyCombi Boiler
Fuel strategyMains Gas.
Renewable energy strategy4kw Photovoltaic panels- split east/west array
Passive Solar strategyWindow proportions optimised using PHPP.
Space cooling strategyDaytime use of MVHR with night purging during heat waves.
Daylighting strategy
Ventilation strategy*Comfort ventilation with heat recovery (winter) * Openable windows (summer)
Airtightness strategy Limeplaster on walls sealed to floor with tape and to windows. All joists and rafters sanded primed and taped at air barrier junction.Proclima intello intelligent membrane used behind service void to seal roof. Party wall foam filled to ensure airtightness and mitigate thermal bypass.Final test 0.27ach
Strategy for minimising thermal bridges Inner leaf of cavity wall underpinned with foamglas blocks to provide continuity with cavity insulation and underfloor insulation. Windows hung outside existing walls in-line with the external insulation.
Modelling strategyWhole house modelling was undertaken in PHPP.
Insulation strategy200mm Graphite EPS external insulation on to filled cavity walls. 100mm PIR board over rafters with 100mm wool batts between rafters and 50mm in service void. 300mm EPS under new 100mm slab. 100mm wool batts on party wall.
Other relevant retrofit strategies
Contextual informationRaising the roof with insulation over rafters was tricky as the house is a semi. A secret gutter was installed to enable this junction.

Building services

OccupancyThree people.
Space heatingSEDBUK A-rated mains gas condensing boiler.
Hot waterCombi gas Boiler
VentilationPaul Focus 200 with rigid steel Lindab ducting
ControlsRoom thermostat
CookingElectric induction hob and oven
LightingLEDs
AppliancesA+ Rated fridge, freezer and washing machine to
Renewable energy generation system4kw PV panels. Split East West array
Strategy for minimising thermal bridgesPsi values have been calculated for internal and external values. External psi-value have been entered into PHPP.

Building construction

Storeys 3
Volume -
Thermal fabric area -
Roof description
Roof U-value -
Walls description
Walls U-value -
Party walls description
Party walls U-value -
Floor description
Floor U-value -
Glazed doors description
Glazed doors U-value - -
Opaque doors description
Opaque doors U-value - -
Windows description
Windows U-value - -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description
Rooflights light transmittance -
Rooflights U-value -

Kingsley Passivhaus : Download Files