Skylarks

download as PDF
Download
as PDF
Deep retrofit of an existing 1960s detached house. The key principles of passive house building design were followed to minimise the primary energy demand of the house.
Images Graphs Figures Description Strategies Building

Skylarks : Project images

Click on image to preview full size

10A.jpg
10B.jpg
11A.jpg
11B.jpg
11C.jpg
6A.jpg
6B.jpg
6C.jpg
6D.jpg
7A.jpg
7B.jpg
7C.jpg
8A.jpg
8B.jpg
9A.jpg
9B.jpg
CO2 emissionsPrimary energy requirement
Energy target
AECB Level 2 Retrofit Standard

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Renewable electricity generation This project has used the contributions from renewable electricity generation equipment to either meet the Retrofit for the Future target or otherwise reduce the Primary energy requirement and CO₂ emissions associated with the project.

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use 3163 kWh/yr 2894 kWh/yr 5057 kWh/yr
Natural gas use- - -
Oil use19572 kWh/yr - -
LPG use45 kWh/yr - -
Wood use2400 kWh/yr 1640 kWh/yr 7665 kWh/yr
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement 151 kWh/m².yr 40 kWh/m².yr 94 kWh/m².yr
Annual CO₂ emissions 33 kg CO₂/m².yr 8 kg CO₂/m².yr 14 kg CO₂/m².yr
Annual space heat demand 91 kWh/m².yr 23 kWh/m².yr 13.3 kWh/m².yr

Renewable energy

Electricity generationForecastMeasured
PV4188 kWh/yr 4188 kWh/yr
Other Renewables Tech--
Electricity consumed by generation -2094 kWh/yr
Primary energy requirement
offset by renewable generation
-7 kWh/m².yr 71 kWh/m².yr
Annual CO₂ emissions
offset by renewable generation
-3 kg CO₂/m².yr 9 kg CO₂/m².yr

Calculation and targets

Whole house energy calculation method PHPP
Other whole house calculation method-
Energy target AECB Level 2 Retrofit Standard
Other energy targets-
Forecast heating load 16 W/m² demand

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test13 October 20221.57m³/m².hr @ 50 Pascals

Project description

StageOccupied
Start date27 September 2021
Occupation date15 April 2022
Location Battisborough Cross Devon  England
Build typeRefurbishment
Building sectorPrivate Residential
Property typeDetached
Construction typeMasonry Cavity
Other construction typeFirst floor is timber frame
Party wall constructionn/a
Floor area 225
Floor area calculation method Treated Floor Area (PHPP)
Building certification  AECB silver standard certified building AECB silver standard certified building

Project Team

OrganisationRob Rickey Design
Project lead personRob Rickey
Landlord or ClientDr. Simon Martin and Dr. Nirosha Gunnatilake
ArchitectRob Rickey
Mechanical & electrical consultant Greengauge Building Energy Consultants
Energy consultantRob Rickey
Structural engineerNigel Ridley
Quantity surveyor
Consultant
ContractorFutureproof Building

Design strategies

Planned occupancyFour persons - at work or school all day
Space heating strategyUse existing radiators heated by Steibel Eltron 7kw air source heat pump. A lower output 4kw modern woodburner with a dedicated air supply was installed to replace the 8kw older model.
Water heating strategy300L Cylinder storage within the thermal envelope. This is heated by an air source heat pump timed to use excess solar PV during midday-early afternoon. This 7kw Steibel Eltron pump efficiency is: 1kw of electrical energy creates a measured output of 3.9kw of heat energy for the hot water system at Skylarks.
Fuel strategyMains electricity. Wood.
Renewable energy strategyUse existing 4kWp array connected to offset any grid use by the air source heat pump, MVHR and all sockets with high use such as dishwasher/washing machine and outside plugs used to slow charge electric vehicles. Measured output is 4188kWH per annum.
Passive Solar strategyGlazing size and orientation optimised using DesignPH and PHPP. Glazed area was reduced to 40% of treated surface area to minimise heat loss and overheating risk.
Space cooling strategyActive by MVHR on summer bypass mode to cool house overnight. Natural cross ventilation due to east west orientation of house with prevailing Westerly coastal breeze. Window reveal depth of 250mm provides shading from direct overhead summer sun. Triple glazed glass has low Thermal Gain value. The 2 flat roof lights have external shade available to minimise gain.
Daylighting strategyRe-use of existing openings.
Ventilation strategyZehnder Q450 MVHR with summer bypass function. This model is a Passivhaus institute certified component and has a 96% heat recovery minimising heat loss by ventilation. The intake and extract ducts to the MVHR unit were kept as short as possible. The insulated ducts were encased in rockwool in their dedicated boxing from outside to the unit (1.2m).
Airtightness strategy Install airtightness layer on the outside of the existing structure using Passive Purple liquid membrane on walls and SmartPly Propassiv OSB on existing rafters. Join systems and windows, with Sega airtightness tapes and insulate outside of this layer.
Strategy for minimising thermal bridges By using external insulation, care taken to ensure that all junctions were formed by insulation meeting insulation. Major junctions modelled in Therm to calculate psi-values. Triple glazed Passivhaus institute certified Progression windows were used. This allows the head and jamb of each window installation to be covered with insulation to improve sci values at these junctions. The sill rests on compact foam.
Modelling strategyModel in Sketchup using DesignPH to optimise glazing ratio and balance insulation, then transfer to PHPP.
Insulation strategy*Remove roofing, install insulation between and above rafters to achieve U-value of 0.156 W/m2K*Insulate masonry walls with wood fibre insulation to achieve U-value of 0.141 W/m2K*Construct new sunroom timber frame wall with infill insulation; U-value of 0.126 W/m2K*Insulate timber framed upper story with wood fibre insulation to achieve U-value of 0.125 W/m2K
Other relevant retrofit strategiesExtend wall and floor perimeter insulation to the integral garage to future-proof this space for inclusion in the heated area of the house.
Contextual information

Building services

OccupancyFamily of four
Space heating7Kw Air source heat pump with radiators. Each radiator is linked to the air source heat pump control to allow continual feedback of room temperature. This is the Easitron Steibel Eltron system.
Hot water7Kw Air source heat pump300L Cylinder storage within the thermal envelope. This is heated by an air source heat pump timed to use excess solar PV during midday-early afternoon. This 7kw Steibel Eltron pump efficiency is: 1kw of electrical energy creates a measured output of 3.9kw of heat energy for the hot water system at Skylarks.
VentilationZehnder Q450 MVHR with summer bypass function. This model is a Passivhaus institute certified component and has a 96% heat recovery minimising heat loss by ventilation. The intake and extract ducts to the MVHR unit were kept as short as possible. The insulated ducts were encased in rockwool in their dedicated boxing from outside to the unit (1.2m).
ControlsAir temperature thermostatic and programmer.Steibel Eltron system with communication between radiators and heat pump. End user can control system remotely. System has a passiv haus insulated house setting and stays in summer bypass mode until measured external temperature drops below 10 degrees over 72 hours.
CookingInduction hob, 2 "AAA" rated electric ovens
LightingLED
Appliances
Renewable energy generation systemSolar PV (12xSunpower panels producing 3.924Kw groos)
Strategy for minimising thermal bridgesExternal insulation on roof, walls and foundation walls below ground. The inward opening Progression windows frame and head have been concealed by insulation.

Building construction

Storeys 2
Volume 563
Thermal fabric area 692
Roof description 100mm Wood fibre between existing joists; 140mm wood fibre insulation on top of airtight deck; standing seam metal roofing
Roof U-value 0.17 W/m² K
Walls description Existing masonry walls: 200mm wood fibre insulation between i-joists; render or timber cladding.Existing timber walls:
Walls U-value 0.14 W/m² K
Party walls description N/A
Party walls U-value 0.00 W/m² K
Floor description Concrete floor slab throughout; partly insulated
Floor U-value 0.25 W/m² K
Glazed doors description 1.Rationel Auraplus triple glazed door
Glazed doors U-value 0.79 W/m² K uninstalled
Opaque doors description Internorm AT400 Aluminium
Opaque doors U-value 0.75 W/m² K uninstalled
Windows description Slavona Progression triple glazed window
Windows U-value 0.68 W/m² K uninstalled
Windows energy transmittance (G-value) 0.542 %
Windows light transmittance 0.74%
Rooflights description Velux triple glazed units
Rooflights light transmittance 0.73%
Rooflights U-value 0.83 W/m² K

Skylarks : Download Files