Rectory Cottage

download as PDF
Download
as PDF
Rectory Cottage is an EnerPhit-certified retrofit stone cottage. Energy performance measures include excavating the original floor to insert insulation (the builders were ex-miners), external wall insulation, triple glazed windows and doors, and a ventilation and heat recovery system. An LPG system boiler and solar thermal panels with integrated controllers were installed. To add to the PHPP challenges the building is in a National Park and a conservation area, and also accommodates the occasional bat....externally. The renovations were designed by a PHPP consultant and experienced architect and the work was carried out by a novice builder and client. Gas meters have been installed which, together with temperature and humidity sensors, will be used to determine the building performance.
Images Graphs Figures Description Strategies Building

Rectory Cottage : Project images

Click on image to preview full size

IMG_0539.jpg
CO2 emissionsPrimary energy requirement
Energy target
EnerPHit

Energy and fuel use

Fuel use by type
Primary energy requirement
CO2 emissions
Renewables

Measured data from renewable generation is not yet available.

Fuel use

 Pre-developmentForecastMeasured
Electricity use - - -
Natural gas use- - -
Oil use- - -
LPG use- - -
Wood use- - -
Other Fuel - - -
 Pre-developmentForecastMeasured
Primary energy requirement - - -
Annual CO₂ emissions - - -
Annual space heat demand - 25 kWh/m².yr -

Renewable energy

Electricity generationForecastMeasured
Renewables Technology--
Other Renewables Tech--
Electricity consumed by generation --
Primary energy requirement
offset by renewable generation
--
Annual CO₂ emissions
offset by renewable generation
--

Calculation and targets

Whole house energy calculation method PHPP
Other whole house calculation method-
Energy target EnerPHit
Other energy targets-
Forecast heating load 12 W/m² demand

Airtightness

 DateResult
Pre-development air permeability test--
Final air permeability test24 March 20150.62m³/m².hr @ 50 Pascals

Project description

StageOccupied
Start date
Occupation date
Location Llangattock Powys  Wales
Build typeRefurbishment
Building sectorPrivate Residential
Property typeDetached
Construction typeStone
Other construction typewith blockwork extensions
Party wall construction
Floor area 141
Floor area calculation method Treated Floor Area (PHPP)
Building certification  Passivhaus certified building Passivhaus certified building

Project Team

Organisation
Project lead personPeter Blood
Landlord or ClientMr and Mrs P Blood
ArchitectSimon Brown
Mechanical & electrical consultant
Energy consultantAlan Clarke
Structural engineer
Quantity surveyor
Consultant
ContractorCraig Morgan

Design strategies

Planned occupancy
Space heating strategyLPG system boiler with programmable controller, fuelled by 47 kg cylinders.
Water heating strategyTwin coil cylinder heated by boiler and solar thermal panels with integrated controllers.
Fuel strategyNo town gas, so opted for LPG cylinders as a more compact solution than oil.
Renewable energy strategySolar PV on adjacent outbuilding, not part of retrofit.
Passive Solar strategyA further south-facing window was added in the refurbishment. Fenestration of the front, east, elevation was largely preserved but new, large, west-facing widows were installed on both floors.
Space cooling strategyLarge thermal mass of original stone walls, MVHR summer bypass. Open the windows at night.
Daylighting strategyEnlarged windows to sitting room and spare bedroom/study. Internal ground floor doors have frosted glass panels.
Ventilation strategyNovus 300 MVHR with ISO frost protection. Touchscreen control in kitchen.
Airtightness strategy Internal floor membrane sealed to existing internal wall plaster. Existing external cement render used as airtightness layer for walls. DA airtightness membrane over OSB on roof, sealed to walls with cement render.
Strategy for minimising thermal bridges Some internal walls removed to reduce heat lost to ground. EWI extended 300 mm below internal floor level. Original chimney stack through roof removed.
Modelling strategyPHPP
Insulation strategyFloors excavated and insulated with 150 mm Ecotherm. 200 mm Plustherm graphited EPS EWI on the smoothed original cement render finish. Weatherproofed with K-rend system. Roof: 100 mm Ecotherm above airtightness membrane and 90 mm Knauf Earthwool insulation between rafters.
Other relevant retrofit strategiesPrior to purchase the property was identified as suitable for EnerPHit refurbishment because of its original external render finish (enabling EWI to be used), its box-like form, and absence of lossy protrusions such as dormer windows. It transpired that the original render finish could be used as the airtightness layer for the walls. Adopting a warm-roof strategy gave easy access to the MVHR in the loft for filter changes.
Contextual informationAlthough Rectory Cottage is located in a conservation area, the original external finish was a cement render over the stone walls. The nature of the external finish was therefore unchanged using EWI with a weatherproof render system. The original window openings of the front elevation were retained.

Building services

Occupancy
Space heating
Hot water
Ventilation
Controls
Cooking
Lighting
Appliances
Renewable energy generation system
Strategy for minimising thermal bridges

Building construction

Storeys 2
Volume 452.4
Thermal fabric area 466
Roof description
Roof U-value 0.15 W/m² K
Walls description
Walls U-value 0.12 W/m² K
Party walls description
Party walls U-value -
Floor description
Floor U-value 0.14 W/m² K
Glazed doors description
Glazed doors U-value - -
Opaque doors description
Opaque doors U-value - -
Windows description
Windows U-value 0.75 W/m² K -
Windows energy transmittance (G-value) -
Windows light transmittance -
Rooflights description
Rooflights light transmittance -
Rooflights U-value -

Rectory Cottage : Download Files